bs_teras wrote:
the opening is targeted on 9 june...
Status as at 4th and 5th June..
- divider not ready
- R&R not ready
- rawang ramp not ready
- road sign not fully installed
- lane painting not fully complete
- fencing not ready (there are dogs and cows patrolling the road)
Definitely not 9 June.. Unless they increase the work force